Saturday, August 17, 2024

MAINTENANCE AND INSPECTIONS OF FIXED CO2 EXTINGUISHING SYSTEMS

MAINTENANCE AND INSPECTIONS OF FIXED CO2 EXTINGUISHING SYSTEMS 

Hello everyone, we are often asked, "What CO2 level is dangerous?" CO2 levels above 40,000ppm (4%) are life threatening. However, there are many other limits placed on carbon dioxide levels depending on your application.

These limits are defined by agencies such as the Occupational Health and Safety Administration (OSHA) and other regulatory bodies.

Safety guidelines:-

The US a workplace safety standard is set by OSHA and it defines gas standards, like CO2. It states that CO2 danger levels begin at 5,000ppm (0.5%) Time Weighted Average (TWA) for an 8-hour period. This means that the average concentration cannot exceed 5,000 ppm over an 8 hour work cycle.

Furthermore, OSHA defines 30,000ppm (3.0%) as it's evacuation threshold.  This means the once the CO2 concentration hits 30,000ppm nobody should be in the space for more than 15 minutes.

Note that carbon dioxide is not generally found at hazardous levels unless there is limited ventilation where gas is being stored or produced, or where the room is considered a confined or enclosed space.

Additional compressed gas guidelines for CO2 include but are not limited to:

1.   Never opening a damaged valve

2.   Avoiding direct skin contact with extremely cold liquids or compressed gases escaping from the cylinder

3.   Never wear watches, rings, or bracelets because they can freeze to exposed skin if splashed by an ultracold gas

4.   Always wear insulated gloves to protect against the cold

At least every six months, (or more frequently if required by an appropriate authority), the mechanical parts of the system should be thoroughly inspected and tested for proper operation by competent personnel. Any electrical detection systems should be tested quarterly in accordance with the requirements of BS 5839-1: 2017.

1. Monthly Inspections

1. At least every 30 days a general visual inspection should be made of the overall system condition for obvious signs of damage, and should include verification that:

1.1 all stop valves are in the closed position;
1.2 all releasing controls are in the proper position and readily accessible for immediate use;
1.3 all discharge piping and pneumatic tubing is intact and has not been damaged;
1.4 all high pressure cylinders are in place and properly secured; and
1.5 the alarm devices are in place and do not appear damaged.

In addition, on low pressure systems the inspections should verify that:

1.6 the pressure gauge is reading in the normal range;
1.7 the liquid level indicator is reading within the proper level;
1.8 the manually operated storage tank main service valve is secured in the open position; and
1.9 the vapour supply line valve is secured in the open position.

2. Annual inspections

The following minimum level of maintenance and inspections should be carried out in accordance with the system manufacturer’s instructions and safety precautions:

2.1        The boundaries of the protected space should be visually inspected to confirm that no modifications have been made to the enclosure that have created un-closeable openings that would render the system ineffective;

2.2        All storage containers should be visually inspected for any signs of damage, rust or loose mounting hardware. Cylinders that are leaking, corroded, dented or bulging should be hydrostatically retested or replaced;

2.3        System piping should be visually inspected to check for damage, loose supports and corrosion. Nozzles should be inspected to ensure they have not been obstructed by the storage of spare parts or a new installation of structure or machinery;

2.4        Check all control valves for correct manual function and automatic valves additionally for correct automatic function. Externally examine containers for signs of damage or unauthorized modification, and for damage to system hoses.

2.5        The manifold should be inspected to verify that all flexible discharge hoses and fittings are properly tightened; and

2.6        All entrance doors to the protected space should close properly and should have warning signs, which indicate that the space is protected by a fixed carbon dioxide system and that personnel should evacuate immediately if the alarms sound. All remote releasing controls should be checked for clear operating instructions and indication as to the space served.

2.7        Carbon dioxide containers, check weigh or use a liquid level indicator to verify correct content of containers. Any showing a loss of more than 10% to be replaced or refilled.

The service life of the cylinders is checked on each visit; every ten years, these are due for Hydrostatic Pressure Testing. When the Hydrostatic Pressure Testing is due, a separate quotation will be issued for this work. The CO2 cylinder hydrostatic test pressure can be anywhere from 3,000 to 10,000 psi. Stored as a liquid at an ambient temperature of 70ºF (21ºC) carbon dioxide has a vapor pressure of approximately 850 psi (5865 kPa). Thus, high pressure cylinders are used for storage, designated as High Pressure CO2.

On each visit to service the electrical detection system, a number of tests and checks, as laid down, are carried out on the control and indicating equipment and the power supply unit output voltage and battery charging rate are measured and recorded.

The system is then tested under mains fail conditions to prove the standby batteries using at least one break glass call point and smoke detector in every zone.

On completion of the test, the battery voltage is measured and recorded, and the system is restored to normal operation.

3. Other minimum recommended maintenance

1. At least biennially (intervals of 2 years ± 3 months) in passenger ships or at each intermediate, periodical or renewal survey in cargo ships, the following maintenance should be carried out.

The following maintenance should be carried out.

1. All high-pressure cylinders and pilot cylinders should be weighed or have their contents verified by other reliable means to confirm that the available charge in each is above 90% of the nominal charge. Cylinders containing less than 90% of the nominal charge should be refilled.

> The liquid level of low-pressure storage tanks should be checked to verify that the required amount of carbon dioxide to protect the largest hazard is available.

2. the hydrostatic test date of all storage containers should be checked. High pressure cylinders should be subjected to periodical tests at intervals not exceeding 10 years. At the 10-year inspection, at least 10% of the total number provided should be subjected to an internal inspection and hydrostatic test.
>> If one or more cylinders fail, a total of 50% of the onboard cylinders should be tested. If further cylinders fail, all cylinders should be tested. Flexible hoses should be replaced at the intervals recommended by the manufacturer and not exceeding every 10 years.

3. the discharge piping and nozzles should be tested to verify that they are not blocked. The test should be performed by isolating the discharge piping from the system and flowing dry air or nitrogen from test cylinders or suitable means through the piping.

The service life of the cylinders is checked on each visit; every ten years, these are due for Hydrostatic Pressure Testing. When the Hydrostatic Pressure Testing is due, a separate quotation will be issued for this work.

On each visit to service the electrical detection system, a number of tests and checks, as laid down, are carried out on the control and indicating equipment and the power supply unit output voltage and battery charging rate are measured and recorded. The system is then tested under mains fail conditions to prove the standby batteries using at least one break glass call point and smoke detector in every zone.

On completion of the test, the battery voltage is measured and recorded, and the system is restored to normal operation.

On the annual visit, the entire system is exhaustively tested.

On completion of any visit, a Service Report and Certificate of Inspection is completed detailing works carried out.

BS 5306-4:2001 further requires that every 12 months a check of enclosure integrity is carried out. If the measured aggregate area of leakage has increased from that measured during installation which would adversely affect system performance, remedial work should be carried out.

The "Authority Having Jurisdiction"

One of the keys to accurately and effectively monitoring to meet codes is to know specifically what your jurisdiction requires. This isn't always easy. Authorities that have jurisdiction over your business can require more prescriptive codes - but not less.

CO2 Meter recommends you contact your local fire inspector (aka the AHJ) and ask specifically what they require. Inspectors are always open to proactive individuals as it demonstrates your desire to meet their codes and keep your staff and the public safe.

Below Snap shoot from NFPA 12 2022 Clause 4.8

If any Both "any doubt" or "any doubts" please write us on ssaintegrate@gmail.com.

Thursday, August 1, 2024

Fire and Smoke Damper ITM

 Fire and Smoke Damper Installation Testing Maintenance

Dampers are located in ductwork and ceiling cavities. Should fire break out, they're designed to close, and so suppress the spread of smoke and fire throughout the building.

Fire, smoke, and combination fire/smoke dampers are crucial pieces of equipment used to reduce the spread of fire and smoke throughout a building. For an overview of the basics on fire and smoke dampers refer to this newly developed fact sheet. As with all fire protection and life safety equipment, fire and smoke dampers must be properly inspected, tested, and maintained to ensure that they will operate when needed.

2015 NFC ITM REQUIREMENTS

The 2015 Edition of the NFC added specific requirements for the inspection, testing and maintenance of dampers. Specifically, clause (b) was added to Sentence 2.2.2.4.(5). Which now reads:

Fire dampers, smoke dampers, combination smoke/fire dampers and fire stop flaps shall be

a) inspected at intervals not greater than 12 months to ensure that they are in place and not obviously damaged or obstructed, and

b) tested in accordance with NFPA 80, “Fire Doors and Other Opening Protectives.”

The NFC now requires that dampers be visually inspected every year and tested in accordance with NFPA 80.

NFPA 80 requires that all access panels be labelled “Fire Damper” with minimum 1” letters. While NFPA 105 requires that all access panels be labelled “Smoke Damper” with minimum ½” letters. Neither Standard specifies a requirement for combination fire/smoke damper.

Fire Dampers

Chapter 19 of NFPA 80, Standard for Fire Doors and Other Opening Protectives, provides the ITM requirements for fire dampers.

Operational Test

An operational test is performed (typically by the installation personnel) right after the damper is installed to confirm the following:

·        Damper fully closes.

·        There are no obstructions to the operation of the damper.

·        There is full and unobstructed access to the damper.

·        For dynamic dampers, the velocity in the duct is within the velocity rating of the damper.

·        All indicating devices are working and report correctly.

·        The fusible link (if equipped) is the correct temperature classification and rating.

Acceptance Testing

An acceptance test is a test of the damper that is completed by a qualified person after the damper is installed, an operational test is completed, and the entire heating, ventilation, and air conditioning (HVAC) system is complete. The acceptance test is performed to confirm the following prior to placing the entire system in service:

·        The damper is not damaged or missing any parts.

·        If actuated, dampers close fully upon disconnection of electrical power or air pressure.

·        If actuated, dampers fully reopen when electrical power or air pressure is reapplied.

·        If non-actuated, the damper closes upon removal of the fusible link and is manually reset to the full-open position.

Testing must be done under maximum airflow after HVAC system balancing, unless acceptance testing is being performed for dampers with fusible links. In that case, it is permitted to turn the fan in the system off.

Periodic Testing

Fire dampers need to be inspected and tested 1 year after the initial acceptance test and then every 4 years, unless the dampers are installed in a hospital, in which case they can be inspected and tested every 6 years.

During the periodic inspection of an actuated fire damper, the following needs to be completed:

·        Confirm that the damper is in the full-open or full-closed position as required by the system design.

·        Visually confirm the damper moved to the full-closed or full-open position when commanded.

·        Visually confirm that the damper returns to the original operating position as required by the system design.

During the periodic inspection of a non-actuated fire damper, the following needs to be completed:

·        Confirm the fusible link is not painted.

·        Confirm the damper fully closes when the fusible link is removed or activated with the damper in the full-open position.

·        Where equipped, confirm that the damper latches in the full-closed position.

·        Confirm that the damper is returned to the full-open and operational position with fusible link installed.

Smoke Dampers

Chapter 7 of NFPA 105, Standard for Smoke Door Assemblies and Other Opening Protectives, provides the inspection, testing, and maintenance requirements for smoke dampers, which are outlined below. Smoke dampers that are part of a smoke control system need to be inspected and tested in accordance with NFPA 92, Standard for Smoke Control Systems.

Operational Test

An operational test is performed after the damper is installed and after the building’s heating ventilation and air conditioning (HVAC) system has been fully balanced to confirm the following:

·        Damper fully closes under both the normal HVAC airflow and non-airflow conditions.

·        There are no obstructions to the operation of the damper.

·        There is full and unobstructed access to the damper.

·        All indicating devices are working and report correctly.

Acceptance Testing

An acceptance test is a test of the damper that is completed by a qualified person after the damper is installed, an operational test is completed, and the entire HVAC system is complete to confirm the following prior to placing the entire system in service:

·        The damper is not damaged or missing any parts.

·        Dampers close fully upon disconnection of electrical power or air pressure.

·        Dampers fully reopen when electrical power or air pressure is reapplied.

Testing must be done under maximum airflow after HVAC system balancing.

Periodic Testing

Smoke dampers need to be inspected and tested 1 year after the initial acceptance test and then every 4 years, unless the dampers are installed in a hospital, in which case they can be inspected and tested every 6 years.

During the periodic inspection, the following needs to be completed:

·        Confirm that the damper is in the full-open or full-closed position as required by the system design.

·        Visually confirm the damper moved to the full-closed or full-open position when commanded.

·        Visually confirm that the damper returns to the original operating position as required by the system design.

Combination Fire/Smoke Dampers

Combination Fire/Smoke Dampers need to meet the requirements for both fire dampers and smoke dampers when it comes to ITM.

Documentation

All inspections and tests of fire, smoke, and combination fire/smoke dampers need to be documented and maintained for at least three test cycles. These documents need to include the following:

·        Location of the damper

·        Date(s) of inspection

·        Name of the inspector

·        Deficiencies discovered, if any

·        Indication of when and how deficiencies were corrected, if applicable

Maintenance

Proper maintenance of fire, smoke, and fire/smoke dampers is crucial to ensure that they remain operational. If a damper is found to not be operational, repairs need to be completed without delay and a periodic test must be completed after the repair is completed to ensure the damper’s operation. All exposed moving parts of the damper need to be lubricated as required by the manufacturer and any reports of an abrupt change in airflow or noise from a duct system needs to be investigated to ensure that it is not related to the damper operation.

Proper inspection, testing, and maintenance of fire, smoke, and fire/smoke dampers ensure they are installed and operating properly in the event of an emergency. For more information about the basics of fire, smoke, and combination fire/smoke dampers, write us ssaintegrate@gmail.com

Manufacturer’s Instructions – ITM Recommendations

Some manufacturers may have additional ITM recommendations. For example, Price Industries recommends “cycling all motorized fire and smoke dampers a minimum of once every 6 months”. It’s important to review the installation, operational and maintenance instructions for any additional ITM activities.

INSTALLATION AND OPERATION INSTRUCTIONS – PER ULC-S112

ULC-S112 Section 14 outlines the installation and operating instructions. (Note that ULC-S112.1 also has similar requirements with some variations which are not provided here). The most notable requirement, in both standards is that a copy of the installation and operating instructions are required to be provided in each shipping container.

The instructions are required to specify all of the following:

·        The type of wall or partition (masonry or gypsum wallboard) or floor, as applicable.

·        The clearances required for expansion of the fire damper, as applicable.

·        The type and thickness of the sleeve material when the sleeve is field assembled.

·        The type and size of fasteners and the spacing of the fasteners used in attaching the fire damper frame to the sleeve (when a sleeve is to be used and is to be field supplied), and perimeter mounting angles to the fire damper frame or the sleeve.

·        The specified means of sealing the damper to ductwork or damper frame, or both, if applicable.

·        The length of the sleeve or frame extending beyond the wall or floor opening.

·        The type of material, size, thickness, and minimum wall/floor overlap of the perimeter mounting angles, and whether or not they are to be welded (or fastened using other means) to each other at the corners.

·        That the connecting ducts shall not be continuous, and shall terminate at the sleeve or frame.

·        The type of duct-sleeve connections (see Figure 1 and Section 12, Duct Impact Test) when sleeve thickness less than 1.6 mm steel is used.

·        Information on connecting the actuator to the power (electric or pneumatic) supply.

·        Any other specific features required for the installation and operation.

For multiple assembly of the dampers, the instructions shall also specify:

·        The method of attaching individual sections together.

·        When any mullions are required, their materials, sizes, locations, and the method of attaching them to the dampers.

·        The maximum size of the multiple assembly that may be assembled.

·        The maximum size of the individual sections that may be attached together.

A copy of the installation and operation instructions should be included in the buildings fire safety plan for each type of damper, along with the initial testing and acceptance documentation. The owner should have documentation including at least the following: location of the damper, model number, date of installation, hourly rating, mounting position, size, leakage rating, maximum velocity, maximum pressure, actuator type, power source, status switch, sleeve construction, access/equipment requirements, any additional notes. This documentation provides information for the ongoing ITM requirements, damper replacement, or building renovation.