FIRE WATER SUPPLY CHECKLIST
pROJECT
INFORMATION
|
|
Project name: |
|
Prepared by: |
|
Checked by: |
|
Date: |
|
general
notes
|
|||
ü |
N/A |
Description |
Remarks |
|
|
Calculations shall be prepared before any
design work |
|
|
|
After
selecting the Mechanical capacity for equipment, electrical data has the
first priority and to be handed over to electrical Department |
|
|
|
All
architectural plans shall be revised form Mechanical point of view as soon as
it is received from the Architect. |
|
|
|
All requirements, Design stages shall be
according to the prepared calculations |
|
|
|
Shaft coordination shall be done with
other MEP systems. |
|
mep
Requirements CHECKLIST
|
|||
ü |
N/A |
Description |
Remarks |
Fire Water tanks Location and
Capacity |
|
||
|
|
Fire Water Tank as per QCD requirements |
|
|
|
Fire water tank is 2 compartment |
|
|
|
Type of the tanks shall be specified
(GRP, Concrete, Sectional) means of access, proper ventilation, equalizing
valves, overflow pipe, vents, water level indicator and drainage system. Fire
tanks shall be provided
with complete appurtenances for
maintenance purposes, drains,
overflow pipe, water level
indicator, tank access, vents, etc. Ensure the tank has two equal
compartments, all pumps are taking suction from both tank and each pump can
be isolated for testing. |
|
Fire Water tanks & Fire Pump
room |
|
||
|
|
Mechanical Pump room shall have as a
separate detail with scale of 1:50 |
|
|
|
Fire Pump room area to be carefully
determined according to QCD requirements and the equipment inside (Main
electric pump, diesel pump, and jockey pump, bulk tank, etc.…) |
|
|
|
Tank compartments served by the pump room
shall have a common wall |
|
|
|
Pump room level shall be lower than the
Water tank by 20 cm minimum (for tank drainage). |
|
|
|
Clear height between the water level and
the pump room bottom of slab 1 m minimum (for access door and overflow line). |
|
|
|
Pump room shall have double leaf door
opening to outside. |
|
|
|
Filling line for Firefighting tanks shall
have the same size as KAHRAMAA tie in Pipe. |
|
|
|
Fire tanks shall have the following: ·
Drain pit ( usually
600X600X200mm) ·
Suction Pipe c/w anti-vortex
plat ·
Tank drain ·
Tank Over flow ·
Filling line (c/w float valve
and shall be near to the access opening) ·
Vent pipe ·
Level indicator ·
Test and drain pipe |
|
|
|
Dimension of the room to verify adequate
housing of the fire pump and related fittings, valves, headers and related
equipment complying with NFPA 20 & 22.
|
|
|
|
Sprinklers inside the fire pump room (if
installed below ground level) and shall be rated as Extra Hazard Group 2. |
|
|
|
Sequence of operations for the fire pump
and Schedule of Equipment |
|
|
|
A
testing line shall
be provided with
flow meter and
isolating valve. Provide details of each component. |
|
|
|
Provide a pump room layout with section
and elevation detail relative to the fire water tank. Ensure at least 0.8
meter clearance in every side of the pumps for maintenance work space. |
|
|
|
Ensure that distance between pump flange
and suction elbow/tee flange is greater than 10 diameter as per NFPA 20. |
|
|
|
Provide bulk tank calculation for diesel
pump. |
|
|
|
|
|
|
|
|
|
ü |
N/A |
Description |
Remarks |
Plan and shafts requirements |
|
||
|
|
Check ZCS and risers location. |
|
DETAILED
DESIGN CHECKLIST
|
|||
ü |
N/A |
Description |
Remarks |
Pipe Materials |
|
||
|
|
Underground main piping shall be HDPE. |
|
|
|
Exposed pipes
and pipes running inside shafts shall be black steel |
|
Cover page |
|
||
|
|
As per FF cover page file |
|
|
|
Legend and Symbols shall be modified to
contain only items in the project. |
|
|
|
Notes Must be read Carefully to match the
project. |
|
|
|
Technical schedule shall be prepared for
All projects, showing: 1-fire tank schedule indicating the
following: area, effective height, volume, capacity, duration, construction
type (steel, concrete), location, accessories. 2- All types of fire pumps indicating the
type of pump, capacity, head and power requirements. 3-Fire Extinguishers schedule indicating
the class (A,B,C,D,K) capacity (lbs./ kg / gal), type (ABC, dry /wet
chemical, CO, foam or others), description (wheeled, cartridge), rating in
terms of A:B:C) and tagging (i.e. FE-1, FE-2). |
|
Standard Details |
|||
|
|
Check that all project standard details
are matching and shown (sprinklers, landing valve, fire hose reel, clean
agent, fire extinguisher etc...) |
|
|
|
Check text size to be readable when
printed (even the DWG. Is N.T.S) |
|
|
|
|
|
Design Criteria |
|||
Plan |
|||
|
|
Check location
of ZCS and fire risers. |
|
|
|
Drain pipe is
installed for ZCS (test and drain valve) connected to separate drain riser. |
|
|
|
Pipe sizes
shall be according to NFPA 13 |
|
|
|
Sprinklers
will be distributed as per NFPA 13 with taking in consideration maximum and
minimum distance between sprinkler and wall and sprinklers with each other. |
|
|
|
Check false
ceiling depth for using double layer sprinkler. |
|
|
|
Side wall
sprinkler will be installed in elevator pit, stairs and ramps. |
|
|
|
Sprinkler will
be installed in garbage chute. |
|
|
|
Branch lines
shall not exceed eight sprinklers. |
|
|
|
For toilets
area 5m2 or higher sprinkler will be installed as per NFPA13. |
|
|
|
In case of
office building or commercial building OS&Y gate valve c/w tamper switch
will be installed at the entrance of office or retail. |
|
|
|
Check ZCS components (OS&Y, CH.V, P.G, F.S,
T&D valve). |
|
|
|
Testing
connection for the most remote area will be installed. |
|
|
|
Landing valve
will be taken from stand pipe riser or combined riser (before ZCS). |
|
|
|
Landing valve
is installed in order of priority : (1)
Firefighting lobby (2) smoke stop
lobby (3) inside staircase and
comply with NFPA 14. |
|
|
|
Fire hose reel
is taken after ZCS. |
|
|
|
Fire hose reel
is distributed in corridor or lobbies provided that each one cover 30m. |
|
|
|
Alarm gong is
placed at the entrance of the building and is connected to alarm check valve
in fire pump room. |
|
|
|
Fire
extinguisher (dry chemical powder) is used for stores, telecom and electric
rooms in floors. |
|
|
|
Fire
extinguisher (wet chemical powder) and fire blanket (4x4) ft. is used for
kitchens and pantries. |
|
|
|
|
|
ü |
N/A |
Description |
Remarks |
Clean agent Details |
|||
|
|
Details shall
be prepared for ALL projects ( small and large projects) |
|
|
|
Foam system is
used for generator room and bulk tank. |
|
|
|
FM200 is used
for fire command center , main telecom ,LV (main electric) ,MV and TX rooms
in case of TX in under ground |
|
Riser Diagram |
|||
|
|
Riser Diagram
shall be prepared for ALL projects (small and large projects) |
|
|
|
Check Riser
Diagram text height shall be readable (even if it is NTS) |
|
|
|
Riser Diagram
shall show all branches and shall have the same order of the plan as
possible. |
|
PRESENTATION
CHECKLIST
|
|||
ü |
N/A |
Description |
Remarks |
|
|
All used blocks shall be as per FF CAD
standard file. |
|
|
|
All Layers (pipes, text, leader, etc...)
shall be as per FF CAD standard file. |
|
|
|
All text shall be using Multi leader with
properties as per FF CAD standard file. |
|
|
|
All text with boundaries shall be as per
FF CAD standard file. |
|
|
|
Text size shall be read at layout as 2.5
regardless the viewport scale. |
|
|
|
All blocks, pipes, fittings, etc... shall
have a proper scaling and dimension ( plan and Schematic) |
|
|
|
Tanks & equipment shall have tag
numbers same as equipment schedule. |
|
Submission
to CIVIL DEFENCE
|
|||
ü |
N/A |
Description |
Remarks |
|
|
Documents. |
|
|
|
Cover page shall be as per FF cover page FF
CAD standard files. |
|
|
|
CAD & PDF drawing. |
|
|
|
Elite Calculations (most demand &
most remote, Hydraulic Calculation Summary & Isometric Drawings). |
|
|
|
Clean agent calculations. |
|
|
|
Comments reply after revision 0 |
|