FIRE WATER SUPPLY CHECKLIST

 FIRE WATER SUPPLY CHECKLIST

pROJECT INFORMATION

Project name:

 

Prepared by:

 

Checked by:

 

Date:

 

 


general notes

ü

N/A

Description

Remarks

Calculations shall be prepared before any design work

 

After selecting the Mechanical capacity for equipment, electrical data has the first priority and to be handed over to electrical Department

 

All architectural plans shall be revised form Mechanical point of view as soon as it is received from the Architect.

 

All requirements, Design stages shall be according to the prepared calculations

 

Shaft coordination shall be done with other MEP systems.

 

 


mep Requirements CHECKLIST

ü

N/A

Description

Remarks

Fire Water tanks Location and Capacity

 

Fire Water Tank as per QCD requirements

 

Fire water tank is 2 compartment

 

Type of the tanks shall be specified (GRP, Concrete, Sectional) means of access, proper ventilation, equalizing valves, overflow pipe, vents, water level indicator and drainage system. Fire tanks shall  be  provided  with  complete  appurtenances  for  maintenance  purposes,  drains,  overflow  pipe, water level indicator, tank access, vents, etc. Ensure the tank has two equal compartments, all pumps are taking suction from both tank and each pump can be isolated for testing. 

 

Fire Water tanks & Fire Pump room

 

Mechanical Pump room shall have as a separate detail with scale of 1:50

 

Fire Pump room area to be carefully determined according to QCD requirements and the equipment inside (Main electric pump, diesel pump, and jockey pump, bulk tank, etc.…)

 

Tank compartments served by the pump room shall have a common wall

 

 Pump room level shall be lower than the Water tank by 20 cm minimum (for tank drainage).

 

Clear height between the water level and the pump room bottom of slab 1 m minimum (for access door and overflow line).

 

Pump room shall have double leaf door opening to outside.

 

Filling line for Firefighting tanks shall have the same size as KAHRAMAA tie in Pipe.

 

Fire tanks shall have the following:

·        Drain pit ( usually 600X600X200mm)

·        Suction Pipe c/w anti-vortex plat

·        Tank drain

·        Tank Over flow

·        Filling line (c/w float valve and shall be near to the access opening)

·        Vent pipe

·        Level indicator

·        Test and drain pipe

 

Dimension of the room to verify adequate housing of the fire pump and related fittings, valves, headers and related equipment complying with NFPA 20 & 22. 

 

Sprinklers inside the fire pump room (if installed below ground level) and shall be rated as Extra Hazard Group 2.

 

Sequence of operations for the fire pump and Schedule of Equipment

 

A  testing  line  shall  be  provided  with  flow  meter  and  isolating  valve.  Provide details of each component.

 

Provide a pump room layout with section and elevation detail relative to the fire water tank. Ensure at least 0.8 meter clearance in every side of the pumps for maintenance work space.

 

Ensure that distance between pump flange and suction elbow/tee flange is greater than 10 diameter as per NFPA 20.

 

Provide bulk tank calculation for diesel pump.

 

 

 

 

 

 

 

 

 

ü

N/A

Description

Remarks

Plan and shafts requirements

 

Check ZCS and risers location.

 

 


DETAILED DESIGN CHECKLIST

ü

N/A

Description

Remarks

Pipe Materials

 

Underground main piping shall be HDPE.

 

Exposed pipes and pipes running inside shafts shall be black steel

 

Cover page

 

As per FF cover page file

 

Legend and Symbols shall be modified to contain only items in the project.

 

Notes Must be read Carefully to match the project.

 

Technical schedule shall be prepared for All projects, showing:

1-fire tank schedule indicating the following: area, effective height, volume, capacity, duration, construction type (steel, concrete), location, accessories.   

2- All types of fire pumps indicating the type of pump, capacity, head and power requirements.

3-Fire Extinguishers schedule indicating the class (A,B,C,D,K) capacity (lbs./ kg / gal), type (ABC, dry /wet chemical, CO, foam or others), description (wheeled, cartridge), rating in terms of A:B:C) and tagging (i.e. FE-1, FE-2).

 

Standard Details

Check that all project standard details are matching and shown (sprinklers, landing valve, fire hose reel, clean agent, fire extinguisher etc...)

 

Check text size to be readable when printed (even the DWG. Is N.T.S)

 

 

 

 

 

Design Criteria

Plan

Check location of ZCS and fire risers.

 

Drain pipe is installed for ZCS (test and drain valve) connected to separate drain riser.

 

Pipe sizes shall be according to NFPA 13

 

Sprinklers will be distributed as per NFPA 13 with taking in consideration maximum and minimum distance between sprinkler and wall and sprinklers with each other.

 

Check false ceiling depth for using double layer sprinkler.

 

Side wall sprinkler will be installed in elevator pit, stairs and ramps.

 

Sprinkler will be installed in garbage chute.

 

Branch lines shall not exceed eight sprinklers.

 

For toilets area 5m2 or higher sprinkler will be installed as per NFPA13.

 

In case of office building or commercial building OS&Y gate valve c/w tamper switch will be installed at the entrance of office or retail.

 

Check ZCS components (OS&Y, CH.V, P.G, F.S, T&D valve).

 

Testing connection for the most remote area will be installed.

 

Landing valve will be taken from stand pipe riser or combined riser (before ZCS).

 

Landing valve is installed in order of priority :

(1) Firefighting lobby      (2) smoke stop lobby       (3) inside staircase and comply with NFPA 14.

 

Fire hose reel is taken after ZCS.

 

Fire hose reel is distributed in corridor or lobbies provided that each one cover 30m.

 

Alarm gong is placed at the entrance of the building and is connected to alarm check valve in fire pump room.

 

Fire extinguisher (dry chemical powder) is used for stores, telecom and electric rooms in floors.

 

Fire extinguisher (wet chemical powder) and fire blanket (4x4) ft. is used for kitchens and pantries.

 

 

 

 

 

ü

N/A

Description

Remarks

Clean agent Details

Details shall be prepared for ALL projects ( small and large projects)

 

Foam system is used for generator room and bulk tank.

 

FM200 is used for fire command center , main telecom ,LV (main electric) ,MV and TX rooms in case of TX in under ground

 

Riser Diagram

Riser Diagram shall be prepared for ALL projects (small and large projects)

 

Check Riser Diagram text height shall be readable (even if it is NTS)

 

Riser Diagram shall show all branches and shall have the same order of the plan as possible.

 

 


PRESENTATION CHECKLIST

ü

N/A

Description

Remarks

All used blocks shall be as per FF CAD standard file.

 

All Layers (pipes, text, leader, etc...) shall be as per FF CAD standard file.

 

All text shall be using Multi leader with properties as per FF CAD standard file.

 

All text with boundaries shall be as per FF CAD standard file.

 

Text size shall be read at layout as 2.5 regardless the viewport scale.

 

All blocks, pipes, fittings, etc... shall have a proper scaling and dimension ( plan and Schematic)

 

Tanks & equipment shall have tag numbers same as equipment schedule.

 

 

Submission to CIVIL DEFENCE

ü

N/A

Description

Remarks

Documents.

 

Cover page shall be as per FF cover page FF CAD standard files.

 

CAD & PDF drawing.

 

Elite Calculations (most demand & most remote, Hydraulic Calculation Summary & Isometric Drawings).

 

Clean agent calculations.

 

Comments reply after revision 0