FM200 Pre-Commissioning Check List
NOTE:
The manufacturing of FM-200 (HFC-227ea / Hydrofluorocarbons (HFC)) is being phased down as part of the AIM Act recently passed by Congress. ... Also known as HFC-227ea in NFPA 2001 Standard, this agent is odorless, colorless, liquefied compressed gas that discharges as an electrically non-conductive, clear vapor.
To monitor the quality of the FM-200 pipework
throughout different stages and before testing and commissioning works taking
place, checklists will be completed by the project team [client, commissioning
manager, designer, and installer/contractor].
The stages at when these checks will be
completed are:
- delivery,
- storage,
- installation &
- pre-commissioning/pre-functional
Once the delivery, storage, installation, and pre-commissioning/functional checks have been completed, the pressure testing can commence.
Delivery Inspection
Once the FM-200 pipework and ancillaries arrive at the site,
usually delivered by a transport company, the following should be checked with
the driver before being accepted into storage.
Any noted damage should be reported immediately in writing to
the manufacturer/supplier, supported with photographs.
REF |
INSPECTION/TASK |
1 |
Supplier's
consolidated delivery ticket is available, showing all equipment and
ancillaries for inspection and being used to check the delivery. |
2 |
A copy of
the order is available for reference and used to review the delivery. |
3 |
Pipework is
packaged with end caps to protect the internal surfaces. |
4 |
Pipework
has the correct wall thickness. |
5 |
Pipework
has suitable flanges. |
6 |
Pipework is
dry internally. |
7 |
Pipework is
not damaged. |
8 |
Pipework
surfaces are clean and not scratched |
9 |
Paint has
been applied to the pipework where required and is in good condition. |
10 |
All
ancillaries are included in delivery as per the order and delivery note |
11 |
Replace any
protection that has been removed |
Storage Inspection
Storage Area
If the FM-200 pipework is to be placed into storage on-site
before installation, there should be an inspection completed checking the
following.
REF |
INSPECTION/TASK |
1 |
The area is
internal and shall not be affected by the weather. |
2 |
If the
pipework & ancillaries are not to be stored internally but externally,
there is sufficient protection to protect it from weather and ambient
conditions. |
3 |
The surface
where the pipework & ancillaries are to be placed is flat. |
4 |
The area is
well covered and protected. |
5 |
The area is
well ventilated and has no risk of high humidity. |
6 |
The area is
clean & dust-free. |
Storage of the FM-200 Pipework & Ancillaries
Before the pipework is placed into storage, the following should
be checked.
[note: due to the risks involved, the gas cylinders shall not be
stored on-site, they shall be delivered and installed just before handover and
documented separately].
REF |
INSPECTION/TASK |
1 |
Pipework
& ancillaries will not be over stacked. |
2 |
Pipework
& ancillaries shall not have materials stacked on them. |
3 |
All
ancillaries shall be placed in a safe and secure location so items do not go
missing or get damaged. |
4 |
Pipework/connection
caps protecting the flanges are not removed. |
5 |
The
pipework shall be raised from the floor to allow airflow and stop the risk of
water ingress. |
Pre-Installation Inspection
Before the pipework & ancillaries are installed, the
following should be checked.
REF |
INSPECTION/TASK |
1 |
The
bracketry is ready and can bear the weight of the installation, and has been
spaced correctly. |
2 |
The
room/area is dry and watertight. |
3 |
The area
being installed is not prone to flooding or ponding of water. |
4 |
The
room/area the pipework will be installed into is clean and dust-free. If
there is dust/construction work, the pipework should be protected from
concrete dust, cement. |
5 |
Check to
ensure that all connection kits containing - gaskets, bolts are available to
allow bolting up of the pipework. |
6 |
Pipework is
clean and free of damage |
Maintenance/Access
REF |
INSPECTION/TASK |
1 |
There is
enough space allowed around and above the pipework once installed to perform
maintenance and remove components, where required [check the manufacturer's
maintenance instructions for requirements] |
Pre-Commissioning Inspection
Once the pipework has been installed and before the functional
testing and commissioning phase, the following shall be checked.
General
REF |
INSPECTION/TASK |
1 |
Pipework
& ancillaries are installed according to the project drawings &
manufacturers' requirements [size, nozzle location]. |
2 |
Discharge
nozzles are installed and oriented per the manufacturer's requirements. |
3 |
Where
nozzle deflectors have been installed, they are positioned according to the
manufacturer's requirements. |
4 |
There is no
risk of potential harm or injury from installing the nozzles and bracketry. |
5 |
There is no
risk of loose objects being stored within the space on shelves, cabinets, or
similar surfaces, near to the discharge nozzles from becoming projectiles. |
6 |
Piping is
free to expand and contract without noise or damage to hangers, joints, or
the building. |
7 |
Pipework
does not put undue stress on ancillaries and equipment, connected and
bracketed to support itself. |
8 |
Seismic
restraints, where required, installed. |
9 |
All piping
supports and hangers meet criteria set out in the specifications &
manufacturers' requirements, including being securely fastened to prevent unwanted
vertical or lateral movement during discharge. |
10 |
The
pipework has been internally inspected to verify that there is no oil or
dirt/debris within it that could cause an issue to the operation of the
system discharge. |
11 |
Any changes
in pipe sizes are made with the proper sized reducing fittings. |
12 |
All
fittings meet specification requirements & manufacturers' requirements. |
13 |
All
fittings and ancillaries are rated correctly and in line with the system's
pressure & manufacturers' requirements. |
14 |
All
equipment requiring maintenance is accessible (valves, junction boxes). |
15 |
Piping does
not block access to equipment that is part of this system or another system. |
16 |
All valves
are installed as per the drawing & manufacturers' requirements. |
17 |
Pipework is
insulated as per the specification and vapor sealed where required. |
18 |
Piping is
installed, ensuring that insulation shall not contact adjacent surfaces. |
19 |
Any pipe
openings are temporarily sealed to maintain piping system cleanliness & integrity
for testing. |
20 |
All
components, including valves and controls, are labeled according to the
project naming convention. |
21 |
Valves/check
valves have been installed according to the manufacturer's requirements and
are in the correct direction. |
22 |
All
pressure gauges installed and display scale as per design &
manufacturers' requirements. |
Thank you so much for sharing such useful information!
ReplyDeleteThanks for your post.
visited moreUganda PVoC Certificate
Nice blog!
ReplyDeleteAre you searching for a service center in Dubai for your Macbook?? Scorpionfix is here, one of the best Apple service center in Dubai.
Surface pro 8 repair in Sharjah
Surface pro service center Sharjah
Surface pro service center Dubai
Macbook repair in Sharjah
Macbook repair in Dubai.
Laptop repair in Dubai
Laptop repair in Sharjah
Surface pro 8 repair in Dubai
macbook service center abu dhabi
macbook repair abu dhabi
Laptop repair abu dhabi
Laptop service center abu dhabi
Apple service center Sharjah
nice
ReplyDelete