METHOD STATEMENT FOR
SPRINKLER PIPING SYSTEM
Wet sprinkler systems may dominate the fire safety market, but
there’s a better solution for certain environments prone to freezing: dry
sprinkler systems. Dry sprinklers provide the coverage you need in areas where
the temperature drops to 40°F or below, without the fear of blocked or burst
pipes. And because they don’t always have water running through most of the
pipe network, they’re also used for structures with sensitive or expensive contents.
NFPA 5000: Building Construction and Safety Code,
the International Building Code (IBC), local ordinances,
and NFPA 101: Life Safety Code – mandate the use of some type
of automatic sprinkler system in buildings based on factors such as the height
and size of the building, its occupancy group, and its occupant load. They are
required in most new commercial buildings that exceed 5,000 square feet and
existing structures that expand to over 12,000 square feet.
1.
Scope:
The scope of this method
statement is to describe the method of installation of sprinkler piping system.
It applicable for Towers, East and West Podiums and Villas. According to NFPA
13, Pipe Schedule System is defined as sprinkler system in which the pipe
sizing is selected from a schedule that is determined by the occupancy
classification and in which a given number of sprinklers are allowed to be
supplied from specific sizes of pipe.
2.
Material
2.1 Sprinkler pipes to ASTM
A536 GR `B’
2.2 Zone Control Valve
2.3 Test and Drain Valves
2.4 Alarm valves
2.5 Pressure gauges
2.6 Flow switches
2.7 Pressure reducing valves
2.8 Water motor gong
2.9 Other associated materials
3.
General Equipment
& Tools
The equipment that will be engaged for Installation of Fire
Fighting works will be
Tool Box
Welding Machine
Drilling Machine with various
Bits
Grinding Machine
Cutting Machine
Threading Machine
Chain Block
Pipe Wrench
Hand Tools-gloves.
Hammer
Portable Lights
Manual Excavation Tools
Removable Barricades
Scaffolding / Mobile scaffold
Ladder
Spirit Level
Screwdriver, Pliers, Spanner.
Marker
Pressure gauge
Level gauge / Spirit level.
Measuring tape
Pressure test pump.
4.
Storage
4.1 All material while
unloading shall be lowered to the ground either manually or with mechanical aid
like crane depending on the quantity of the pipe and should not be dropped to
the ground.
4.2 For pipes, timber supports
shall be placed beneath at equal distance.
4.3 Pipes shall be stacked on a
flat surface with adequate supports.
4.4 End caps of pipes shall be
in place until removed for installation.
4.5 While stacking, it shall be
ensured that pipes of bigger sizes are placed below and smaller sizes on top.
4.6 The pipes will be stacked
in the site store on a proper stand on wooden loft on a flat surface at a
height not exceeding 1.7m. From the bottom layer.
4.7 All pipes shall be covered
and shall not be exposed to direct sunlight.
4.8 All other items such as
valves, gauges, switches shall be kept on racks within site stores and shall be
segregated as per size, model, type etc. for easy retrieval.
4.9 Any items found damaged or
not suitable as per project requirements shall be removed from site. If
required to store temporarily, they shall be clearly marked and stored
separately to prevent any inadvertent use.
5.
Preparation
5.1 Check and ensure all
drawings used for installation are latest and approved for construction.
5.2 Check the coordination of
piping layout with other services and reflected ceiling and resolve problems,
if any.
5.3 Check Type of Material, Size of Material, Make of Material as
per approved makelist.
5.4 Mark the pipe routing on
the ceiling as per approved drawings.
5.5 After checking in case of any damages observed during
inspection, the concern report will be issued and Material shall be returned to
the supplier for replacement.
5.6 The sprinkler pipe size from the water supply source to a
sprinkler shall be not less than 3/4 of an inch (20 mm) in
diameter. Threaded adapter fittings at the point where sprinklers are attached
to the piping shall be not less than 1/2 of an inch (15 mm) in
diameter.
6.
Installation
6.1 Fix supports and hangers
with approved material, as per approved layout drawings.
6.2 Cut all excess hanger rods
to leave only 25mm lengths below the support for final adjustment of levels, if
required.
6.3 Machine cut the pipes
square to required length and ream the pipes to remove burrs and clean
thoroughly before installation.
6.4 Pipe work upto 50mm shall
have threaded joints and pipes 765mm and above shall be with grooved coupling
joints. The pipe work shall be grooved and installed as per coupling
manufacturers instruction and grooving equipment as supplied by manufacturer
shall be used.
6.5 Install pipe work at heights and to gradients shown on
approved drawings, in a neat and tidy manner. The Pipe route should be
min 500mm away from wall.
6.6 Holesaw cutter shall be
used to cut holes in the pipe work where required for fixing mechanical Tees
etc.
6.7 PVC Sleeves of suitable
sizes shall be provided at wall crossings and fire stopping with approved
material shall be completed.
6.8 Only standard fittings
shall be used for changes in directions, reduction in pipe sizes, Tee joints,
etc. Only long radius bends shall be used where required.
6.9 Expansion couplers shall be
installed at location where piping crosses the building expansion joints (Refer
Annexure-I for manufacturer’s recommendations).
6.10 All vertical pipes shall
be installed plumb with at least 25mm clearance from the wall / surface.
6.11 Install valves,
supervisory switches, flow switches, pressure gauges etc. as per approved
drawings and manufacturer’s instruction.
6.12 Install drain valves at
all low points as shown on approved drawings and ensure that water can be
drained from all sections of pipe work.
6.14 Inspectors test drain
valves of suitable size shall be provided at the farthest point in the system
in each zone as per approved drawings.
6.15 Check and ensure easy
access is available for maintenance and removal of all components such as
valves, switches etc.
6.16 The droppers for sprinkler
heads are installed at location as per approved layout / coordinated drawings.
6.17 Plug or cap-off all open
ends in the piping during the installation phase.
6.18 Flush and clean the entire
piping with clean water until the system is clean.
6.19 Install correct type of
sprinkler heads as per approved drawings and manufacturers instruction.
6.20 Clean the pipe work
thoroughly to remove all dirt, soil, oil, etc. and apply one coat of primer.
6.21 Provide identification and
flow directional arrows to the pipe work, valves and other components as per
approved submittals / details.
6.22 The entire installation
shall be supervised, checked and certified prior to testing and commissioning
of the system.
6.23 The details of the entire
installation of the system shall be inspected and approved by the Authority or any good foundation.
7.
Testing &
Commissioning
7.1 The entire pipe work shall
be hydrostatically pressure tested as per method statement Ref. ETA/MS/P-011.
7.2 The final testing and
commissioning of the system shall be carried out as per Method Statement Ref.
ETA/MS/P-014.
8.
Water Supply Treatment
8.1 NFPA 13-9-1.5 states “In
areas with water supplies known to have contributed to micro biologically
influenced corrosion (MIC), water supplies shall be tested and appropriately
treated prior to filling or testing of metallic piping systems”.
8.2 But, the chemical
composition of DEWA water clearly shows that there is no microbiologically
influenced corrosion. As water from DEWA is filled in the fire protection
system, water treatment is not required for the wet system (Annexure-V).
9.
Safety
9.1 Warning signs shall be
placed at required location during pressure testing of the pipe work and
barriers where required to protect other services.
9.2 All precautions shall be
followed as per established project safety procedures.
10.
Records
10.1 Work Inspection Request
(WIR) duly signed by Consultants.
10.2 Installation check lists
signed by QA/QC.
10.3 Installation report /
certification by specialist fire protection contractor.
10.4 Test Certificate for
Piping System
You have provided a richly informative article about fire extinguisher testing It is a beneficial article for me and also helpful for those who are searching for this kind of information. Thanks for sharing this information here.
ReplyDeleteNice blog!
ReplyDeleteAre you searching for a service center in Dubai for your Macbook?? Scorpionfix is here, one of the best Apple service center in Dubai.
Surface pro 8 repair in Sharjah
Surface pro service center Sharjah
Surface pro service center Dubai
Macbook repair in Sharjah
Macbook repair in Dubai.
Laptop repair in Dubai
Laptop repair in Sharjah
Surface pro 8 repair in Dubai
macbook service center abu dhabi
macbook repair abu dhabi
Laptop repair abu dhabi
Laptop service center abu dhabi
Apple service center Sharjah